HVAC completed & electrical is in progress. Change to mechanical chase framing approved by homeowner. Brick installation is in progress. Note: weather has been difficult due to the cold temperatures and rain slowing progress.
DENZIN
Friday, November 11, 2011
Thursday, November 3, 2011
Nov 4 update
Roofing completed
Rough plumbing completed
HVAC & electrical in progress
Target rough inspection by end of next week.
Brick starting 11-7
Rough plumbing completed
HVAC & electrical in progress
Target rough inspection by end of next week.
Brick starting 11-7
Tuesday, October 25, 2011
Oct 25 update
Addition rough frame completing today. Rough plumb completed today. Electrical scheduled for friday 10/28 HVAC scheduled for Monday 10/31
Progress on roofing. Tear-off complete & shingles about 40% complete. Rain on the way the next three days. Target to complete with 2 days of good weather.
Progress on roofing. Tear-off complete & shingles about 40% complete. Rain on the way the next three days. Target to complete with 2 days of good weather.
Friday, October 21, 2011
Tuesday, October 11, 2011
Thursday, October 6, 2011
Denzin
Project summary
Contact information
Project mgr: Dennis Wood 517-759-9507
Production mgr: Jasen Brielmaier 517-206-2276
Project consultant:Kevin Busch 734-476-7681
Designer: Sharon Rejc 517-499-6109
Schedule:
Pre-construction date: 8/5
Start date: 8/22
Target completion date:12/25
Contact information
Project mgr: Dennis Wood 517-759-9507
Production mgr: Jasen Brielmaier 517-206-2276
Project consultant:Kevin Busch 734-476-7681
Designer: Sharon Rejc 517-499-6109
Schedule:
Pre-construction date: 8/5
Start date: 8/22
Target completion date:12/25