Friday, November 11, 2011

November 10 update

HVAC completed & electrical is in progress. Change to mechanical chase framing approved by homeowner. Brick installation is in progress. Note: weather has been difficult due to the cold temperatures and rain slowing progress.

Thursday, November 3, 2011

November 4 update

Nov 4 update

Roofing completed
Rough plumbing completed
HVAC & electrical in progress
Target rough inspection by end of next week.
Brick starting 11-7

Tuesday, October 25, 2011

Oct 25 update

Addition rough frame completing today. Rough plumb completed today. Electrical scheduled for friday 10/28 HVAC scheduled for Monday 10/31

Progress on roofing. Tear-off complete & shingles about 40% complete. Rain on the way the next three days. Target to complete with 2 days of good weather.

Thursday, October 6, 2011

Denzin

Project summary
Contact information
Project mgr: Dennis Wood 517-759-9507
Production mgr: Jasen Brielmaier 517-206-2276
Project consultant:Kevin Busch 734-476-7681
Designer: Sharon Rejc 517-499-6109

Schedule:
Pre-construction date: 8/5
Start date: 8/22
Target completion date:12/25